F-35 Warplane Costs Driven Up by Production Choice: U.S. General

February 18, 2013

A decision to start production of Lockheed Martin Corp's F-35 fighter jet before it was fully tested has driven up the $396 billion cost of the troubled project and increased risks, the U.S. general heading development of the warplane has said.
 
The head of the Pentagon's F-35 program office, Lieutenant General Chris Bogdan, told Australian Broadcasting Corporation (ABC) television that major challenges had been created by a production and test approach known as "concurrency".

"A large amount of concurrency, that is, beginning production long before your design is stable and long before you've found problems in tests, creates downstream issues where now you have to go back and retrofit airplanes and make sure the production line has those fixes in them," Bogdan told ABC's Four Corners program late on Monday.